St Phil's Eastwood site plans
Our St Phil's Eastwood site has been under planning and development since 2016. This post aims to provide our members with the overall site plans - past and future!
Stage 1
Currently, we are completing stage 1 which included many renovations and additions over the past 5 years:
Stage One Works Completed
- Development Application for master plan $60,000
- Construction Certificate for master plan $126,000
- Heritage Church Building - replace floor and refurbish $150,000
- Children's Ministry Centre - structural repairs, modify, refurbish $163,000
- Children's Ministry Centre - new kitchen, refurbish adjacent spaces $24,000
- Construct maintenance shed $12,000
- War Memorial Hall refurbish $33,000
- War Memorial hall solar panels $11,000
- Administration office - modify, refit & refurbish $9,500
- Perimeter child safe fencing $42,000
- War Memorial Hall - air conditioning $34,000
- Children;'s Ministry Centre (1906 hall) - air conditioning $20,000
- Main courtyard and grounds - major paving and landscaping $60,000
- Children's Playground $56,000
- New toilet block and access ramp $210,000
- Carpark entry and landscape $47,000
Stage One Works to Complete
- Carpark grading and sealing $100,000
- Detention tank for whole site $150,000
Photos of Stage 1 completed so far:
CMC before renovation
CMC during renovation
CMC after renovation - eastern deck
CMC after renovation - inside
CMC after renovation - western verandah
Driveway (carpark) under construction
Driveway - during construction
Driveway and Gardens - after construction
Fencing - carpark area
Fencing - playground area
Playground
Landscaping - under construction
Playground and Landscaping - completed
New shed
War Memorial Hall - Air conditioning
Stage 2
The stage 2 works are the final stage and include the demolition of the 2 Sunday School rooms and the rear room of the CMC, followed by the construction of a large two-level facility with a 330 seat auditorium, offices, meeting rooms, a parent room, toilets, kitchen and large foyer.
The picture below will help to give an idea of what this is expected to look like. The cost for this work is currently estimated to be around $5 million. This will allow for much more capacity on site as well as allowing us to hold many more language-based services and children and youth programs on-site at the same time.
When our stage 1 plans are complete, we will continue to raise funds for this major building plan as God allows.